## @SmallCapSnipa (Small Cap Snipa) · 09-25 12:05 · ♥118 ↻10 💬4 $CIFR EXTENDS BARBER LAKE LEASE TERM TO 20 YEARS + OVER $9 BILLION

The Texas data center rises from $3.8 billion to over $9 billion. Cipher expects approximately $5.2 billion in incremental contracted revenue. https://t.co/naTKmN5UW1 https://x.com/SmallCapSnipa/status/2103455838635741288

## @AIStockSavvy (Hardik Shah) · 09-25 11:45 · ♥49 ↻3 💬5 📢 𝗝𝗨𝗦𝗧 𝗜𝗡: $CIFR CIPHER Extends Barber Lake Data Center Contracts to 20 Years, Revenue Tops $9 Billion

👉 𝗞𝗲𝘆 𝗛𝗶𝗴𝗵𝗹𝗶𝗴𝗵𝘁𝘀:

➤ 𝗖𝗶𝗽𝗵𝗲𝗿 extends Barber Lake's contracted lease duration from 𝟭𝟬 to 𝟮𝟬 years.

➤ Total contracted revenue increases from $𝟯.𝟴 𝗯𝗶𝗹𝗹𝗶𝗼𝗻 to over $𝟵 𝗯𝗶𝗹𝗹𝗶𝗼𝗻.

➤ A leading 𝗔𝗜 𝗹𝗮𝗯 commits to an additional 𝟭𝟬-year lease.

➤ New commitment adds approximately $𝟱.𝟮 𝗯𝗶𝗹𝗹𝗶𝗼𝗻 in contracted revenue.

➤ 𝗙𝗹𝘂𝗶𝗱𝘀𝘁𝗮𝗰𝗸's existing lease was amended alongside the new commitment.

➤ Data halls will be delivered from 𝗤𝟰 𝟮𝟬𝟮𝟲 through 𝗤𝟭 𝟮𝟬𝟮𝟳.

➤ First rent commencement is expected during 𝗤𝟰 𝟮𝟬𝟮𝟲.

➤ Cipher will bear the first $𝟯𝟱𝟵.𝟯 𝗺𝗶𝗹𝗹𝗶𝗼𝗻 of excess costs.

➤ Tenant will reimburse 𝟱𝟬% of qualifying costs above that threshold.

👉 𝗪𝗵𝘆 𝗧𝗵𝗶𝘀 𝗠𝗮𝘁𝘁𝗲𝗿𝘀:

➤ More than $𝟵 𝗯𝗶𝗹𝗹𝗶𝗼𝗻 of contracted revenue provides greater long-term visibility.

➤ Twenty-year commitments demonstrate sustained demand for 𝗵𝘆𝗽𝗲𝗿𝘀𝗰𝗮𝗹𝗲 𝗔𝗜 infrastructure.

➤ The agreement significantly extends Barber Lake's contracted economic life.

➤ Phased rent commencement could begin generating revenue from 𝗤𝟰 𝟮𝟬𝟮𝟲.

👉 𝗘𝘅𝗽𝗲𝗿𝘁 𝗦𝘁𝗮𝘁𝗲𝗺𝗲𝗻𝘁:

𝗧𝘆𝗹𝗲𝗿 𝗣𝗮𝗴𝗲, Chief Executive Officer:

“Extending Barber Lake’s contracted life from 10 to 20 years and adding approximately $5.2 billion of contracted revenue reflects the enduring value of the infrastructure we're building,” said Tyler Page, Chief Executive Officer. “Barber Lake was designed as a long-lived, mission-critical asset, and securing a firm commitment that extends well beyond the original lease term demonstrates the long-term utility and strategic relevance of the campus. We believe this transaction underscores the quality and enduring strength of our sites, as well as the durability of demand for hyperscale computing capacity.” https://x.com/AIStockSavvy/status/2103450882406760538

## @WOLF_Financial (WOLF) · 09-25 11:55 · ♥34 ↻8 💬3 Cipher Digital $CIFR extended its Barber Lake data center contracts from 10 to 20 years, lifting total contracted revenue from $3.8B to more than $9B.

The extra 10 years are backed by a binding commitment from an unnamed AI lab and add about $5.2B of revenue. https://t.co/TJtBF7AnLw https://x.com/WOLF_Financial/status/2103453210250007040

## @Sam_Badawi (Sam Badawi) · 09-25 12:20 · ♥44 ↻3 💬2 $CIFR extended its Barber Lake data center lease from 10 to 20 years, increasing total contracted revenue from $3.8B to over $9B.

The additional 10-year commitment with a leading AI lab is expected to add roughly $5.2B in contracted revenue. https://t.co/u9aZSIG983 https://x.com/Sam_Badawi/status/2103459550292820022

## @MitchMartan98 (Mitchell Martan | TLI) · 09-25 11:56 · ♥37 ↻0 💬1 $CIFR great news for bulls:

Cipher extended the contracted life of its Barber Lake data center from 10 to 20 years, increasing total contracted revenue from $3.8B to more than $9B

Cipher will absorb the first $359.3M of cost overruns above the original budget, while the tenant will reimburse 50% of costs above that threshold through additional rent over the lease term. https://x.com/MitchMartan98/status/2103453646075670682